plus Created with Sketch. ! arrow-down arrow-left arrow-right arrow-up Asset 9Asset 7Asset 2 Group 2 Created with Sketch. Rectangle 11 Copy 4 Created with Sketch. Asset 6 close Asset 5 Icon/news/default Asset 20 arrow Created with Sketch. edit Group Created with Sketch. Icon/Learning/Active Icon/Learning/Inactive Shape Asset 10 instagram linkedin Asset 8 Icon/news/default menu send-2 Created with Sketch. Asset 3 pin Asset 14 search share Asset 15Asset 16Asset 19 twitter Asset 11

New renewables figures underline need for federal government measures

A new Clean Energy Council report released today shows sluggish financial commitments in new large-scale renewable energy projects over the course of 2023 continued into the third quarter of the year.

A new Clean Energy Council report released today shows sluggish financial commitments in new large-scale renewable energy projects over the course of 2023 continued into the third quarter of the year.

The Clean Energy Council, the peak body for the renewable energy industry, today released its Q3 Renewable Projects Quarterly Report, confirming that 2023 has been a challenging year for grid-scale renewable energy projects, reaching a total of 509 MW from financially committed projects thus far.

During Q3 2023, investment in new large-scale renewable energy generation projects remained slow, with just two new generation projects totalling 161 MW of capacity achieving financial commitment – the fourth-lowest result since the Clean Energy began tracking project data in 2017.
The latest report provides detailed insights into investment activity within Australia’s clean energy and storage investment pipeline, showing that:

  • Large-scale storage projects saw a decrease in financial commitments during Q3 when compared to the strong previous quarter, with just 13 MW added in the most recent quarter.
  • Three generation projects commenced construction during the quarter, comprising 86MW of additional capacity, while one project reached the commissioning stage, contributing a total of 75 MW.
  • Renewable energy generation and storage projects attracted a total of $150 million during Q3 2023 – the fourth-lowest quarterly total for financial commitments since 2017.

"These numbers are a clarion call for strong and decisive action, and we welcome the Federal Government’s commitment to bringing forward the necessary generation in order to make sure that we can deliver the low-cost, clean electricity we need to replace ageing coal-fired generation,” Clean Energy Council Chief Executive, Kane Thornton, said.

“Between now and 2030, Australia needs a substantial increase in financial commitments for large-scale renewable projects, in the order of 6.9 GW per year to achieve the Federal Government’s target of 82 per cent by 2030.

“Investment in renewable energy has been in gradual decline since the Renewable Energy Target – a policy that delivered substantial new investment - was met in 2020. The rate of investment slowed more dramatically over the past year as a result of higher project costs, complex permitting processes, a congested grid and intensifying global competition in the race to net zero.

“While renewable energy remains the lowest cost form of new generation, there is a clear role for government to facilitate the enormous levels of investment needed to transition our energy system, particularly in an era of significant global competition, due to incentive packages like the US Inflation Reduction Act.

“We can unleash the strong investor interest in Australia with the right policy settings to address the barriers to investment, and we look forward to working with the Federal Government on the implementation details of its new Capacity Investment Scheme for renewable energy generation.”

The Clean Energy Council recently released its Power Playbook, a strategic package of 45 recommendations to the Federal Government designed to ensure Australia gets back on track in meeting its targets and to provides a structure for a future Renewable Energy Superpower Masterplan.

These include measures to drive investment in higher large-scale renewable generation, and allocate more resources between federal, state and territory governments to expedite project assessment processes, and the delivery of 10,000 km of new transmission lines.

Click here to read the full report

ENDS